Ticket #1849 (s2c_design_ok unplanned_task) — at Version 11

Opened 16 years ago

Last modified 15 years ago

UNPLANNED_APP_TESTING_R0

Reported by: deyan Owned by: vanya
Priority: major Milestone: M11_BETA3
Component: SOPHIE_END_PRODUCT Version: 2.0
Keywords: Cc:
Category: END_PROD Effort:
Importance: Ticket_group:
Estimated Number of Hours: 0 Add Hours to Ticket: 0
Billable?: yes Total Hours: 0
Analysis_owners: vanya, deyan Design_owners: vanya
Imp._owners: vanya Test_owners:
Analysis_reviewers: dido Changelog:
Design_reviewers: todor Imp._reviewers: deyan
Test_reviewers: Analysis_score: 4.5
Design_score: 3 Imp._score: 3
Test_score: 0

Description (last modified by deyan) (diff)

UNPLANNED_APP_TESTING_R0 - effort - 3d

Change History

comment:1 Changed 16 years ago by deyan

  • Owner set to deyan
  • Status changed from new to s1a_analysis_started
  • Analysis_owners set to vanya, deyan

comment:2 Changed 16 years ago by vanya

  • Description modified (diff)

comment:3 Changed 16 years ago by vanya

  • Status changed from s1a_analysis_started to s1b_analysis_finished

30m

comment:4 Changed 16 years ago by vanya

  • Design_owners set to vanya

comment:5 Changed 16 years ago by dido

  • Status changed from s1b_analysis_finished to s1c_analysis_ok
  • Analysis_reviewers set to dido
  • Analysis_score changed from 0 to 4.5

Analysis reviewed 4.5p (10m)

comment:6 Changed 16 years ago by vanya

  • Owner changed from deyan to vanya
  • Status changed from s1c_analysis_ok to s2a_design_started

comment:7 Changed 16 years ago by vanya

  • Status changed from s2a_design_started to s2b_design_finished

comment:8 Changed 16 years ago by todor

  • Status changed from s2b_design_finished to s2c_design_ok
  • Design_score changed from 0 to 3
  • Design_reviewers set to todor

the test plan is sufficient but this task is outdated, it's supposed to be finished before 2009.08.07, despite that the requirement "Test plan for current build (2009-08-07)" won't be fulfilled the design will pass in order to have at least some sample books and testplan for them.

comment:9 Changed 16 years ago by vanya

  • Status changed from s2c_design_ok to s3a_implementation_started
  • Imp._owners set to vanya

comment:10 Changed 16 years ago by vanya

  • Status changed from s3a_implementation_started to s3b_implementation_finished

comment:11 Changed 16 years ago by deyan

  • Status changed from s3b_implementation_finished to s2c_design_ok
  • Imp._score changed from 0 to 1
  • Description modified (diff)
  • Imp._reviewers set to deyan
  • The task does not meet it's requirements.
    • Test plan for current build (2009-08-07)
    • Test plan report
    • Books created by execution of testcases

You met only the third requirement, but since there are no executed testcases (or I didn't see) I'm not sure what exactly you did

  • The implementation is not done according to the design.
    • In the design section, 3 books are described, attached are 4 books. This is not a problem at all, but supposes you've not been concentrated (because design describes 3 books named Testbook 1, Testbook 2, Testbook 4. Also, design says:
      • Testbook 1
        • add new pictures - 893 (BMP)
      • Testbook 2

926 - edit frame rotation
938 - edit frame border size
936 - edit frame border color
855 - edit page border color
857 - edit page border size
911 - add a PDF file
922 - resize frame to fit into the page
942 - add an image as a background
edit border style for the pages - 855, 857

I did not see these in corresponding book (note that I've reviewed Book 2 + Book 3 for the Testbook 2 list)
I couldn't review 3rd book because of hardcoded paths, but i'll fix this and review it when you finish your implementation.

Note: See TracTickets for help on using tickets.