Version 2 (modified by deyan, 16 years ago) (diff) |
---|
Analysis team working process
Overview
The responsibilities of the Analysis team are:
- Rescheduling tasks for the next iteration
- Creating tickets for the unplanned tasks
- Adding importances to the tickets in the schedule
- Analysing the tasks of the next Iteration
- Reviewing testing done by the Release team
- Updating and improving PLATFORM_STANDARDS_ANALYSIS
Opening
After the sprint opening the Analysis team should:
- Create the Iteration page for the next sprint
- Add importances to the tasks
- Discuss if there are tasks with bad schedule or estimate and add them for discussion on the weekly meeting.
- Create a custom Iteration page for the Analysis team
Choosing tasks
- On weekly meetings each team member presents:
- What has he/she done
- What he/she plans to do
- Are there any impediments
- Proposals for discussion topic
- On progress check each team member explains what is done based on what he/she declared on the weekly.
- Impediments are added to the Internal Backlog
- Specific questions (that do not affect the whole team) are examined on inter team meetings that are scheduled or on mail group.
- Inter team meetings can be requested by every team member on any time.