[[BackLinksMenu]] = Analysis = == Overview == Input the three unplanned tasks. Arrange the reports and specificate their situation. Fix dates of the milestones. Structure to write a final report. == Task requirements == The sub-tasks for this revision are: * Add unplanned tasks * [wiki:BASE_MODEL_FRAME_CONTENT_R0] * [wiki:CORE_MVC_BASE_R0] * [wiki:BOOK_WINDOW_R0] [[BR]] to the Iteration page. Please note dependencies and priorities in [wiki:SCHEDULE_WBS_DEPENDENCIES_R1], these requirements must be satisfied for added tasks too. Leave the old ticket and create a new one. In the old ticket provide a link to the new one. In the LOG wiki page write down that the task has failed and provide a link to the new Ticket.[[BR]] ^Consider how to add them - by adding new revisions to the wbs or editing the page. Note that changing revisions will probably cause more issues.^ * Design a structure for iteration reports. * Arrange the reports. Create a folder for each iteration (may be done later for more convenient work - folder for the current iteration may be done at the beginning of it.) * Review current dates of the milestones. See the start date of Iteration2 and current Iteration Calendar. Recheck the milestone length, calculate new dates. Fix the dates in [source:/manage/sched/Sprints.txt]. Consider renaming Sprints.txt -> sprints.txt. You may also add sprint requirements in this document, or add them in a wiki page (if so - consider which). == Task result == A wiki page, maintenance of wiki pages and other process documents. == Implementation idea == Create [wiki:REPORTS] with report requirements. Include requirements for daily (See [source:/manage/reports/0README.txt] and iteration reports. Point the way to check if the report has "bad lines". == Related == [wiki:ITERATION_02] [[BR]] [source:/manage/reports/] [[BR]] [source:/manage/reports/0README.txt] [[BR]] [source:/manage/sched/Sprints.txt] [[BR]] [wiki:SCHEDULE_MAINTENANCE_R0] [[BR]] == How to demo == Show added tasks from [wiki:ITERATION_02]. Explain implementation - was the page manually edited or re-generated (this should be explained in Implementation section too). Show Sprints.txt (or sprints.txt) and explain iteration lengths. Explain maintained items from Related section. = Design = * Create a wiki page => [wiki:REPORTS] * Add a Manually added section of the Iteration page. List there the unplanned tasks and create tickets for them. * Add "later" resolution in the resolutions section of the admin panel of trac. * Leave old tickets as "later" and provide links to the new unplanned ones. * Change the milestones dates: * one week more for the first 3 milestones. * extend the 4^th^ milestone with one week. It should finish on the 30^th^ of December. * the milestones after the 4^th^ milestone are not affected. * the Christmas holiday will be lessened a little so that we are on schedule. = Implementation = * [wiki:REPORTS Reports] - a wiki page which contains the reports requirements. These applies to both daily and iteration reports. * Added unplanned tasks at the bottom of the [wiki:ITERATION_02] * link in the old tickets are now pointing to the new ones and the old are leaved as later. * [source:/manage/sched/sprints.txt new sprints schedule] * here are the milestones changed accordingly [http://asteasolutions.net:7080/sophie2/admin/ticket/milestones Milestones in trac] * later resolution added [http://asteasolutions.net:7080/sophie2/admin/ticket/resolution here] - use later when a task is not done on schedule. It means that the task goes into the next iteration. = Testing = = Comments = = Log = [[Include(wiki:SCHEDULE_MAINTENANCE_R1_LOG)]]