Analysis:

  • Verify the existing dependencies in work breakdown structure document(make automatic script to check if the revisions are correct in the related tasks).
  • Add more dependencies for base tasks.
  • Check manually if the created schedule is possible(this can be done by the generated exports or task juggler calendars).

Design:

  • Dependencies are stored in resources ODS in a column called depends.
  • It is not necessary to explicitly say that A depends on C when A depends on B and B depends on C.
  • In most of the cases every subtask of a task depends on ....COMMONS subtask of the same task.
  • Task may depend on task with subtasks or only on a set of subtasks of a task.
  • Since all Tasks have unique names, the name of a task is enough to determine the dependencies.
  • After dependencies are put in the ODS document, all the document should be exported in the WBS document and task juggler calendars should be generated to check the consistency of the dependencies.