wiki:SCHEDULE_WBS_TIME_ALLOC_R0

Version 8 (modified by deyan, 17 years ago) (diff)

--

Analysis

Overview

The whole project depends on correct time allocation, so you have to follow these rules:

  • add revisions to the rest of the tasks carefully ( search for "more()" in the python file )
  • the sprint effort must depend on the resources (developers and QA-s availability) for this sprint
  • use the exported files from sophie2-wbs.py for information

Task requirements

  • The time allocation should be done according to the whole time for the project and should not exceed it.
  • Every task should be divided in three phases (base version, intermediate version, final version).
  • Every phase of a task should be divided by parts called revisions.
  • The sum of the time of all revisions of a task should be equal to the time allocated for the whole task itself.
  • The sum of the time of all tasks should be equal to the time allocated for the whole project.
  • Every base version of a task should begin in the time interval assigned for the beginning of a task(RED zone - see resources.ods for details).
  • Every intermediate version of a task should begin in the time interval assigned for it (YELLOW zone - see resources.ods for details).
  • Every final version of a task should begin in the interval assigned for it (GREEN zone - zone - see resources.ods for details).

Task result

  • an understandable schedule in an appropriate form, so that it is easily maintainable (a table for example).

Implementation idea

  • create a Open Office Spreadsheet for easy manipulation.

How to demo

  • open the resources.ods table and browse through the sheets.
  • see the time allocated for every revision (the middle of the table).
  • see the overall time allocated for every task (the most right-hand column).
  • see the zones (RED, YELLOW, GREEN) in the top-most row to see the beginning, intermediate and finel phase of a task.
  • see zeros bellow the top-most column - they represent that a milestone's time is divided among tasks and that neither more nor less time is assigned for the milestone.

Design

The goal is to synchronize the effort allocations in sophie2-wbs.py to the resources.ods.

  • Create new sheets
    • Platform
    • Core
    • Base
    • Main
    • Extra
    • SCS
    • S2S
    • Supporting
    • End_Prod
  • For each sheet do the following
    • First row should be the same as in alloc sheet
    • Second row should be the same as the corresponding row in alloc sheet (ex. for Platform sheet row 2 should be copied row 3 from alloc sheet)
    • Third row - cells c3..p3 should contain "=X2-SUM(X4:X24)

When this table is ready, each task can be imported in this table. In row 3 can be seen easily how much days are remaining for this milestone for this group of tasks. Use the Output sheet to move the desired rows to the others.

Implementing

  • resulted in a table called resources.ods in the old repository.

Log

  • Analyzing : Pavlina, Todor(done: 15 mins)
  • Designing : Deyan(done:1h)
  • Implementing :Deyan(5d), :-Peko(545 mins)
    • Review : 3.5 by Tanya
  • Testing :