  • SCS_ISSUE_TRACKER_SETUP_R0

    v6 v7  
    1111 
    1212Design: 
     13 
     14 * Types: 
     15  * Planned_Task - this is a task from the schedule. It has four phases: Analysing, Designing, Implementing and Testing. These four are repeated three times during the project and these are: initial (which represents the base version of the task), intermidiate (at this point the task should be more or less completed) and final (here all the parts of the task should be fully consistent and polished). 
     16  * Unplanned_Task - this is a task that is not a part of the schedule so far. Things that appear throughout the project will be put here. 
     17  * Bug - this represents an inconsistency of a task until its final version. 
    1318 * Milestones are already defined. These include: 
    1419  * m1 - milestone 1 
     
    2429  * b3 - beta 3 
    2530  * rel - release 
     31