Ticket #1536 (closed planned_task: obsolete)
GLOBAL_SPEC_STRUCTURE_R2
Reported by: | Astea | Owned by: | deyan |
---|---|---|---|
Priority: | 3 | Milestone: | M05_PRE5 |
Component: | GLOBAL_SPECIFICATION_ARTIFACTS | Version: | 2.0 |
Keywords: | Cc: | ||
Category: | SUPPORT | Effort: | 2 |
Importance: | 0 | Ticket_group: | |
Estimated Number of Hours: | Add Hours to Ticket: | ||
Billable?: | Total Hours: | ||
Analysis_owners: | mitex, deyan | Design_owners: | deyan |
Imp._owners: | deyan | Test_owners: | |
Analysis_reviewers: | kyli | Changelog: | |
Design_reviewers: | kyli | Imp._reviewers: | |
Test_reviewers: | Analysis_score: | 3.5 | |
Design_score: | 4 | Imp._score: | 4 |
Test_score: | 0 |
Description
wiki page: GLOBAL_SPEC_STRUCTURE_R2 - effort: 2d
Change History
comment:1 Changed 16 years ago by pav
- Importance changed from 0 to 90
- Design_score set to 0
- Imp._score set to 0
- Test_score set to 0
- Analysis_score set to 0
comment:2 Changed 16 years ago by deyan
- Design_score set to 0
- Milestone changed from M04_PRE4 to M05_PRE5
- Imp._score set to 0
- Test_score set to 0
- Analysis_score set to 0
Moving to the next iteration
comment:3 Changed 16 years ago by mitex
- Owner changed from Astea to mitex
- Analysis_owners set to mitex
changed owner
comment:4 Changed 16 years ago by deyan
- Owner changed from mitex to deyan
- Status changed from new to s1a_analysis_started
- Analysis_owners changed from mitex to mitex, deyan
comment:5 Changed 16 years ago by deyan
- Status changed from s1a_analysis_started to s1b_analysis_finished
finished
comment:6 Changed 16 years ago by kyli
- Status changed from s1b_analysis_finished to s1c_analysis_ok
- Analysis_reviewers set to kyli
- Analysis_score changed from 0 to 3.5
3,5p. I find the ideas for implementation of all related tasks together and for creating a visual tree very good, but do not personally agree with the idea of moving the DND table (it would be good if all the specifications are kept together). Also, nothing has been told about the keyboard shortcuts and for allocating the specification documents from the last iterations (if any). Just a note, it would be useful to pay attention to the user interactions related documents, since they would be needed in several tasks.
comment:7 Changed 16 years ago by deyan
- Design_owners set to deyan
- Status changed from s1c_analysis_ok to s2a_design_started
thanks for the feedback
comment:8 Changed 16 years ago by kyli
- Status changed from s2a_design_started to s2b_design_finished
- Design_score changed from 0 to 4
- Design_reviewers set to kyli
4p. Very good and descriptive design. A note for the implementor: Creating a new specification document should be displayed in our Internal Backlog (the "Documents" table) and maybe in the "ImportantDocs" section.
comment:9 Changed 16 years ago by deyan
- Status changed from s2b_design_finished to s2c_design_ok
- Imp._owners set to deyan
Thanks for the feedback, i'll note this on some maintenance task.
comment:10 Changed 16 years ago by deyan
- Status changed from s2c_design_ok to s3a_implementation_started
You forgot to change the status
comment:11 Changed 16 years ago by deyan
- Status changed from s3a_implementation_started to s3b_implementation_finished
finished
comment:12 Changed 16 years ago by todor
i began to review this task
comment:13 Changed 16 years ago by todor
- Status changed from s3b_implementation_finished to s3c_implementation_ok
implementation is good and follows strictly the design.
comment:15 Changed 15 years ago by deyan
- Status changed from s3c_implementation_ok to closed
- Resolution set to obsolete
Batch update from file query-obsoleted.csv