Ticket #47 (closed planned_task: obsolete)

Opened 17 years ago

Last modified 15 years ago

PLATFORM_NFR_USABILITY_R0

Reported by: Astea Owned by: deyan
Priority: 3 Milestone: M02_PRE2
Component: SOPHIE_PLATFORM Version: 2.0
Keywords: Cc:
Category: unknown Effort: 2.5
Importance: 10 Ticket_group:
Estimated Number of Hours: Add Hours to Ticket:
Billable?: Total Hours:
Analysis_owners: deyan Design_owners: deyan
Imp._owners: deyan,dan visel Test_owners:
Analysis_reviewers: Changelog:
Design_reviewers: peko Imp._reviewers: pav
Test_reviewers: Analysis_score: 0
Design_score: 4 Imp._score: 3.5
Test_score: 0

Description

wiki page: PLATFORM_NFR_USABILITY_R0 - effort: 2.5d

Change History

comment:1 Changed 16 years ago by deyan

  • Owner changed from Astea to deyan
  • Status changed from new to analyzing

taken

comment:2 Changed 16 years ago by deyan

  • Status changed from analyzing to analyzed

done 3h, did a research on wikipedia - common issues, term meanings, etc.

comment:3 follow-up: ↓ 4 Changed 16 years ago by todor

  • Status changed from analyzed to analysis_accepted

3 by todor. There were some mistakes and problems in formating (now fixed). The quotes should be in the "Related" section, not in the overview.

comment:4 in reply to: ↑ 3 Changed 16 years ago by deyan

Replying to todor:

3 by todor. There were some mistakes and problems in formating (now fixed). The quotes should be in the "Related" section, not in the overview.

PLATFORM_STANDARDS_ANALYSIS Please give comments about where the quotes should be after reading this document. "Related - Here should be listed related tasks that might be useful. You should link previous revisions of this task. You may list useful external links too."

comment:5 Changed 16 years ago by deyan

  • Status changed from analysis_accepted to designing

taken

comment:6 Changed 16 years ago by deyan

  • Status changed from designing to designed

designed, 3h

comment:7 Changed 16 years ago by peko

  • Status changed from designed to design_accepted

comment:8 Changed 16 years ago by deyan

  • Status changed from design_accepted to implementing

taken

comment:9 Changed 16 years ago by deyan

  • Status changed from implementing to implemented

done 4h the main part of the task was in the design and analysis section, worked on the task 7h (de+im)

comment:10 Changed 16 years ago by milo

  • Status changed from implemented to s3b_implementation_finished

comment:11 Changed 16 years ago by pavlina

  • Status changed from s3b_implementation_finished to s3c_implementation_ok

3.5 by Pav. It is good for now. May be we should change the format of the document in the next revisions because now it is not very well-formed for reading.

comment:12 Changed 16 years ago by pavlina

  • Design_score set to 0
  • Imp._reviewers set to Pavlina
  • Imp._score set to 3.5
  • Test_score set to 0
  • Analysis_score set to 0

comment:13 Changed 16 years ago by deyan

  • Design_owners set to deyan
  • Imp._owners set to deyan,dan visel
  • Analysis_owners set to deyan

added owners

comment:14 Changed 16 years ago by peko

  • Category set to unknown
  • Design_score changed from 0 to 4
  • Design_reviewers set to peko

comment:15 Changed 16 years ago by deyan

  • Imp._reviewers changed from Pavlina to pav

Batch update from file newimport.csv

comment:16 Changed 15 years ago by deyan

  • Status changed from s3c_implementation_ok to closed
  • Resolution set to obsolete

Batch update from file query-obsoleted.csv

Note: See TracTickets for help on using tickets.