Ticket #1584 (closed unplanned_task: obsolete)
UNPLANNED_OVERVIEW_R0
Reported by: | deyan | Owned by: | kyli |
---|---|---|---|
Priority: | major | Milestone: | M02b_PRE2b |
Component: | PROJECT_COMMUNITY | Version: | |
Keywords: | Cc: | ||
Category: | Effort: | 3 | |
Importance: | 50 | Ticket_group: | |
Estimated Number of Hours: | Add Hours to Ticket: | ||
Billable?: | Total Hours: | ||
Analysis_owners: | deyan,boyan | Design_owners: | kyli |
Imp._owners: | kyli | Test_owners: | |
Analysis_reviewers: | Meddle, Palvina | Changelog: | |
Design_reviewers: | todor | Imp._reviewers: | todor |
Test_reviewers: | Analysis_score: | 3.5 | |
Design_score: | 3 | Imp._score: | 3 |
Test_score: | 0 |
Description
Change History
comment:2 Changed 16 years ago by deyan
- Owner set to deyan
- Status changed from new to s1a_analysis_started
- Analysis_owners set to deyan
comment:3 Changed 16 years ago by deyan
- Status changed from s1a_analysis_started to s1b_analysis_finished
40m analysis finished
comment:4 Changed 16 years ago by todor
- Status changed from s1b_analysis_finished to s1c_analysis_ok
3.5p by todor. Good analysis, but there were some sentences with vague meaning. Fixed now.
comment:6 Changed 16 years ago by boyan
- Status changed from s1c_analysis_ok to new
- Analysis_reviewers set to boyan
- Analysis_score set to 2
- Test_score changed from 3.5 to 0
- Design_score set to 0
- Imp._score set to 0
2p by boyan. Some of the task requirements are related to the UNPLANNED_DEVELOPMENT_OVERVIEW_R0 task. This task should only be about Sophie2 (project overview, project structure, about, license, etc.) and not the development process (only a link to the DEVELOPMENT_OVERVIEW should be provided).
comment:7 Changed 16 years ago by boyan
- Owner changed from deyan to boyan
- Status changed from new to s1a_analysis_started
- Analysis_owners changed from deyan to deyan,boyan
taken for improvement
comment:8 Changed 16 years ago by boyan
- Status changed from s1a_analysis_started to s1b_analysis_finished
- Analysis_score changed from 2 to 0
comment:9 Changed 16 years ago by pavlina
- Status changed from s1b_analysis_finished to s1c_analysis_ok
- Analysis_reviewers changed from boyan to Meddle, Palvina
- Analysis_score changed from 0 to 3.5
May be you should put somewhere in the start page or in the developers home a link to this page
comment:10 Changed 16 years ago by kyli
- Owner changed from boyan to kyli
- Status changed from s1c_analysis_ok to s2a_design_started
comment:11 Changed 16 years ago by kyli
- Status changed from s2a_design_started to s2b_design_finished
done (50m).
comment:12 Changed 16 years ago by todor
- Design_owners set to kyli
- Design_score changed from 0 to 3
- Design_reviewers set to todor
- Status changed from s2b_design_finished to s2c_design_ok
the design is ok. define where the overview will be situated. may be more explanation of the structure is needed, are the sections going to be different pages or chapters for example.
comment:13 Changed 16 years ago by kyli
- Status changed from s2c_design_ok to s3a_implementation_started
- Imp._owners set to kyli
comment:14 Changed 16 years ago by kyli
- Status changed from s3a_implementation_started to s3b_implementation_finished
done(70m)
comment:15 Changed 16 years ago by todor
- Status changed from s3b_implementation_finished to s2c_design_ok
- Imp._score changed from 0 to 2
- Imp._reviewers set to todor
failed due to request
comment:16 Changed 16 years ago by kyli
- Status changed from s2c_design_ok to s3a_implementation_started
comment:17 Changed 16 years ago by kyli
- Status changed from s3a_implementation_started to s3b_implementation_finished
Reason for the request: there was no explanations to the links; some important information was missing.
The project schedule was described, edition structure and project goal added. The structure of the document was changed. The user documentation (which I believe is most important for the overview) is still unfinished, so the page would be more nice-looking in its later revisions.
comment:18 Changed 16 years ago by todor
- Status changed from s3b_implementation_finished to s3c_implementation_ok
- Imp._score changed from 2 to 3
it's ok now but it took too many effort to be completed
comment:19 Changed 15 years ago by deyan
- Status changed from s3c_implementation_ok to closed
- Resolution set to obsolete
Batch update from file query-obsoleted.csv
Added component