PLATFORM_STANDARDS_DESIGN_R1

Reported by: Astea Owned by: boyan
Priority: 3 Milestone: M03_PRE3
Component: SOPHIE_PLATFORM Version: 2.0
Keywords: Cc:
Category: PLATFORM Effort: 1
Importance: 20 Ticket_group: GROUP_PLATFORM_STANDARDS_R0
Estimated Number of Hours: Add Hours to Ticket:
Billable?: Total Hours:
Analysis_owners: deyan Design_owners: boyan
Imp._owners: boyan Test_owners:
Analysis_reviewers: peko Changelog:
Design_reviewers: deyan Imp._reviewers: deyan
Test_reviewers: Analysis_score: 3.5
Design_score: 3.5 Imp._score: 3.5
Test_score: 0

Description

wiki page: PLATFORM_STANDARDS_DESIGN_R1 - effort: 1d

Change History

comment:1 Changed 16 years ago by deyan

  • Category set to PLATFORM
  • Design_score set to 0
  • Imp._score set to 0
  • Test_score set to 0
  • Analysis_score set to 0

Adding category

comment:2 Changed 16 years ago by peko

  • Importance changed from 0 to 20

comment:3 Changed 16 years ago by deyan

  • Owner changed from Astea to deyan
  • Status changed from new to s1a_analysis_started

taken

comment:4 Changed 16 years ago by deyan

  • Status changed from s1a_analysis_started to s1b_analysis_finished

1h

comment:5 Changed 16 years ago by peko

  • Status changed from s1b_analysis_finished to s1c_analysis_ok
  • Analysis_reviewers set to peko
  • Analysis_score changed from 0 to 3.5

Fine!

comment:6 Changed 16 years ago by boyan

  • Owner changed from deyan to boyan
  • Status changed from s1c_analysis_ok to s2a_design_started

taken for design

comment:7 Changed 16 years ago by boyan

  • Design_owners set to boyan

forgot to fill custom field

comment:8 Changed 16 years ago by boyan

  • Status changed from s2a_design_started to s2b_design_finished
  • Analysis_owners set to deyan

done in 15m (quickly because it was similar to the design of UNPLANNED_PLATFORM_STANDARDS_GENERAL_R0)

comment:9 Changed 16 years ago by boyan

  • Design_owners set to boyan
  • Analysis_owners set to deyan

Due to a bug(?) in Trac, the design owner field was not successfully updated the last time.

comment:10 Changed 16 years ago by boyan

  • Ticket_group set to GROUP_PLATFORM_STANDARDS_R0

grouping tasks

comment:11 Changed 16 years ago by deyan

  • Status changed from s2b_design_finished to s2c_design_ok
  • Design_score changed from 0 to 3.5
  • Design_reviewers set to deyan
  • Imp._score changed from 0 to 3.5
  • Imp._reviewers set to deyan

Old task, implementation is finished and is acceptable.

comment:12 Changed 16 years ago by deyan

  • Status changed from s2c_design_ok to s3c_implementation_ok

comment:13 Changed 16 years ago by deyan

  • Imp._owners set to boyan

comment:14 Changed 15 years ago by deyan

  • Status changed from s3c_implementation_ok to closed
  • Resolution set to obsolete

Batch update from file query-obsoleted.csv