Open sophie2-wbs.py and:
- decompose the tasks further in work breakdown structure (read the rules in the beginning of the document)
- look up for tasks with too small or too big effort and correct them
- add missing tasks and comments
- verify and finalize the document
Analysis
Overview
The goal of this task is to decompose the tasks to subtasks with less effort.
Task requirements
( Taken from /manage/sched/sophie2-wbs.py Rules section)
Task rules
- It should be clear what a given task is!
- Sub-tasks should not overlap!
- Sub-tasks should cover 100% of the parent task.
- Each task should have either:
- Several revisions.
- >=2, <=7 sub tasks
- Super tasks which contains sub-tasks (not a revisions) should not need work for themselves.
- If it looks like it needs, define a child-task that covers this.
- Try to keep to entity/feature driven spec.
- No end task (with revisions only) should have more than 10 effort.
- No task should have less than 1 effort.
- No revision should have less than 0.5 effort.
- Names are global! It should be clear 0.5 effort.
- Names are global! It should be clear what the task is, without its context.
Task result
Schedule meeting listed requirements.
Implementation idea
Open /manage/sched/sophie2-wbs.py and look for:
- Tasks with less than 1 effort
- Revisions with less than 0.5 effort
- Tasks with same names.
- Unclear task names.
- Subtasks do cover < 100% of the parent task.
- Subtasks do overlap each other.
- Child tasks (final) with effort more than 7
- Child tasks (final) with effort less than 2
Note that in some cases effort <=2 and >=7 is permissible.
Related
SCHEDULE_WBS_TIME_ALLOC_R0 SCHEDULE_WBS_DEPENDENCIES_R0 SCHEDULE_WBS_EXPORTS_R0
How to demo
(In this section you must add instructions for the demo of the task.)
Design
Open sophie2-wbs.py and:
- decompose the tasks further in work breakdown structure (read the rules in the beginning of the document)
- look up for tasks with too small or too big effort and correct them
- add missing tasks and comments
- verify and finalize the document
Implementation
(Implementation results should be described and linked here (from the wiki or the repository)
Testing
Log
(Link the log of the task here)