Analysis

Overview

During this revision of the task we must create this iteration's schedule.

Task requirements

  • Create page for this iteration
  • Add the tasks for this iteration
    • unfinished tasks from the previous sprint
    • unplanned tasks
    • remote tasks (done by steve and dan)
    • server tasks from the next sprint
  • Sort them according to their importance in such manner that if task B depends on task A, task A must be higher in the iteration page

Task result

The result of this task must be sorted iteration page including all tasks for this iteration.

Implementation idea

The unfinished tasks from previous sprints are already sorted (you may use that order). The tasks from the next sprints can be with lower priority respectively lower on the iteration page.

SCHEDULE_MAINTENANCE_R0
SCHEDULE_MAINTENANCE_R1
SCHEDULE_WBS_DEPENDENCIES_R1
See manage/reports/m02b/0m02b-opening.txt for creating the new tickets.

How to demo

Show the iteration page and explain your order criteria.

Design

See the ticket comment.

Implementation

Created the iteration page ITERATION_02b. Decided to use queries as we do not use task logs anymore. {

Related Tickets

Status: closed (49 matches)

Ticket Summary Owner Status Type Component Priority Effort Importance
#219 CORE_LOGGING_R0 boyan closed planned_task CORE_FUNDAMENTALS 3 1 20
#375 APP_FILE_DIALOGS_R0 boyan closed planned_task APP_PLUGIN 3 0.5 20
#1589 UNPLANNED_USER_DOC_STRUCTURE_R0 danvisel closed unplanned_task SOPHIE_END_PRODUCT major 2 90
#1590 UNPLANNED_USER_DOC_SAMPLE_R0 danvisel closed unplanned_task uncategorized major 1 50
#1538 GLOBAL_SPEC_MANAGING_R1 deyan closed planned_task GLOBAL_SPECIFICATION_ARTIFACTS 3 2 60
#1576 testticket deyan closed feature uncategorized major 4 50
#1582 UNPLANNED_TEST_TRACKING_MAINTENANCE_R1b deyan closed unplanned_task PROJECT_COMMUNITY major 2 90
#285 BASE_MODEL_TEXTS_R0 htomov closed planned_task BASE_BOOK_MODEL 3 1 20
#5 PLATFORM_STRUCTURE_R1 kyli closed planned_task SOPHIE_PLATFORM 3 2 10
#16 PLATFORM_INFRASTRUCTURE_EXTRAS_R0 kyli closed planned_task SOPHIE_PLATFORM 3 1 10
#51 PLATFORM_NFR_EFFIECENCY_R0 kyli closed planned_task SOPHIE_PLATFORM 3 1 10
#1580 UNPLANNED_DEVELOPMENT_OVERVIEW_R0 kyli closed unplanned_task SOPHIE_PLATFORM major 3 90
#1584 UNPLANNED_OVERVIEW_R0 kyli closed unplanned_task PROJECT_COMMUNITY major 3 50
#298 BASE_RESOURCE_COMMONS_R0 meddle closed planned_task BASE_RESOURCE_MODEL 3 1.5 30
#392 APP_LAYOUT_ALTERNATIVE_R0 meddle closed planned_task APP_PLUGIN 3 1 20
#1293 S2S_CORE_SECURITY_R0 meddle closed planned_task S2S_CORE 3 1 80
#389 APP_LAYOUT_MYDOGGY_R0 nvasilev closed planned_task APP_PLUGIN 3 1 20
#192 PRO_LIB_UTILS_R0 orliin closed planned_task PRO_LIB_EXTRAS 3 1 20
#631 PAGE_SCENE_IMPL_COMMONS_R0 pap closed planned_task PAGE_WORK_AREA 3 2 20
#70 PLATFORM_DEPLOYMENT_BUILD_MAVEN_R0 pavlina closed planned_task SOPHIE_PLATFORM 3 1.5 80
#109 PLUGIN_EDITIONS_STRUCTURE_R1 pavlina closed planned_task PLUGIN_ARCHITECTURE 3 2 50
#244 BASE_DIALOGS_R0 pavlina closed planned_task BASE_GUI_LIB 3 0.5 20
#395 APP_PLUGIN_STARTUP_R0 pavlina closed planned_task APP_PLUGIN 3 0.5 50
#1303 S2S_PERSISTENCE_COMMONS_R0 pavlina closed planned_task S2S_PERSISTENCE 3 1 80
#1322 S2S_DEPLOY_TECHNOLOGIES_R0 pavlina closed planned_task S2S_DEPLOYMENT 3 2 90
#196 PRO_LIB_INSPECTOR_R0 peko closed planned_task PRO_LIB_EXTRAS 3 1 20
#226 CORE_ADDITIONS_R0 peko closed planned_task CORE_ADDITIONS 3 3 20
#240 BASE_LAYOUT_R0 peko closed planned_task BASE_GUI_LIB 3 1.5 20
#258 SCENE_COMMONS_R0 peko closed planned_task BASE_SCENE 3 0.5 30
#264 SCENE_POINT_R0 peko closed planned_task BASE_SCENE 3 2 20
#587 PAGE_SELECTOR_R0 peko closed planned_task BOOK_PAGES 3 0.5 20
#622 AUTHOR_PAGE_WORK_AREA_R0 peko closed planned_task PAGE_WORK_AREA 3 1 20
#625 READER_PAGE_WORK_AREA_R0 peko closed planned_task PAGE_WORK_AREA 3 1 20
#635 PAGE_SCENE_IMPL_MAIN_R0 peko closed planned_task PAGE_WORK_AREA 3 1 20
#1577 UNPLANNED_CORE_MVC_BASE_R0 peko closed unplanned_task CORE_FUNDAMENTALS major 4
#1586 UNPLANNED_FEATURE_SCHEDULE_R0 sriggins closed unplanned_task PROJECT_COMMUNITY major 2 99
#1587 UNPLANNED_FEATURE_SCHEDULE_REVIEW_R0 sriggins closed unplanned_task PROJECT_COMMUNITY major 3 97
#1588 UNPLANNED_FEATURE_SCHEDULE_DELIVERY_R0 sriggins closed unplanned_task PROJECT_COMMUNITY major 1 95
#126 PRO_LIB_CORE_COMMONS_R0 Tanya closed planned_task PRO_LIB_CORE 3 3 30
#268 SCENE_AUDIO_POINT_R0 Tanya closed planned_task BASE_SCENE 3 0.5 20
#272 SCENE_VIDEO_POINT_R0 Tanya closed planned_task BASE_SCENE 3 0.5 20
#538 BOOK_BOTTOM_PANEL_R0 Tanya closed planned_task BOOK_VIEW 3 0.5 20
#1578 UNPLANNED_BASE_MODEL_FRAME_CONTENT_R0 Tanya closed unplanned_task BASE_BOOK_MODEL major 2
#1585 UNPLANNED_FAQ_R0 Tanya closed unplanned_task PROJECT_COMMUNITY major 1 50
#20 PLATFORM_STANDARDS_GENERAL_R1 todor closed planned_task SOPHIE_PLATFORM 3 1 80
#1403 SCS_REPO_MIGRATE_R1 todor closed planned_task PROJECT_COMMUNITY 3 1 90
#1420 SCS_WIKI_SETUP_R1 todor closed planned_task PROJECT_COMMUNITY 3 1.5 40
#1581 UNPLANNED_SCHEDULE_MAINTENANCE_R1b todor closed unplanned_task SCHEDULE major 2 99
#1583 UNPLANNED_REPO_MAINTENACE_R1b todor closed unplanned_task SOPHIE_PLATFORM major 2 80

}

Testing

Comments

Creating a IterationTemplate may be useful.